THE WELCOME BUILDING

SEPTEMBER 2017

The Welcome Building

The Welcome Building in Bishop Auckland consists of a new viewing tower and central ticketing hall for the The Auckland Project. It acts as an access point and gateway to the wider site whilst also giving views over the town and landscape setting. The tower – a timber framed structure – is now well under way on site.

The building team has worked tirelessly and with the highest level of precision, to build the in-situ concrete lift shaft. Working from the ground up seemed to take an age.

Meanwhile, the enormous larch glulam beams have been carefully crafted and manually grey-oiled in the joiner’s workshop.

The frames are now being lifted into position on site and suddenly the building can be seen. Almost in an instant. As if the past four years had happened in the blink of an eye.

We are so excited and proud – even – to see this fantasy project becoming real at last. But with completion on the horizon, time seems to now move all too fast.

A SITE FOR SAURIIS

JANUARY 2017

A Site for Sauriis

Our proposal to redevelop the grounds of the Natural History Museum is due to start on site this month. The work to the main entrance – the first of three phases – will introduce level access to this area for the first time while also restoring the Grade-I listed fabric to its former glory.

The works include changing levels, repaving the forecourt, restoring railings, installing planting, and repairing or reinstating original terracotta details across the site.

Ahead of this, the main entrance and central hall of the Museum are now closed while both teams gear up for construction – including some unusual enabling works. As part of these works Dippy the diplodocus has now been dismantled ahead of going on tour around the country; to be eventually recast in bronze for the next phase of our project.

The railings have now been removed for off-site restoration and re-painting:

And scaffolding is also going up for the removal of display cases and various specimens:

This will need to go up again halfway through construction of Phase 1 allow for delivery of the blue whale skull through our active site. Here it is just before it left the Museum.

If you’re wondering how that that will fit through the front doors, the answer’s simple: the same way the elephants do.

Phase 1 is due to complete mid-July ahead of the main entrance reopening to the public shortly after. In the meantime, there’s a pop-up conservation studio in the Darwin Centre – which we highly recommend – where you can see the conservationists at work restoring the whale’s bones.